Four Season Healthcare – The Maltings

Following a late night emergency call-out it was discovered that one of the care homes existing boilers had been isolated resulting in the remaining boiler being unable to cope with the demand.

CMS quoted to install 2 new high efficiency Potterton Sirius 3 WH 60 boilers, as well as replacing the existing flue. Prior to the installation commencing CMS’ own mobile trailer plant was taken to site, hooked up the home’s existing heating network to ensure that heating and hot water were maintained throughout the installation.

The job was completed on budget and within 4 days by the CMS East Midlands team of expert engineers.